Projects
Surface Construction - Asphalt
Adventure Playground Cycle Track
WORK COMPLETED
- All Stormwater drainage & Drinking Water.
- Concrete & Kerbing.
- Asphalting.
- Ready lawn, Street furniture, Shade sales.
QUICK FACTS
VALUE: $456,000
DURATION: October 2017- December-2017 (3 Months)
LOCATION: Gisborne, NZ
Surface Construction - Chip Sealing
East Cape Road Upgrade
Siteworx have mobilized a team onsite at the East Cape to upgrade an 8.5km section of what is currently a gravel road – we are upgrading it to chip-seal, removing all the existing culverts, and reinstalling new ones – expected completion date is Christmas 2020.
Phase 1 – drainage – is complete, with the team currently working on Phase 2: Heavy Metaling. We also have a team from Higgins onsite who are giving us a hand with stabilizing the road.
QUICK FACTS:
- 8.5km of road
- 45 concrete culverts to replace
- Duration: September 2020 – December 2020
(4 months) - 5 Team Members
Surface Construction - Concrete Placing
Oneroa Walkway – W2W
The Oneroa Walkway is part of Gisborne’s popular boardwalk is located along the dunes between Midway and Waikanae beaches. This walkway addition was to help make crossing the road safer for pedestrians and vehicles alike – the raised crossings created a designated crossing area for pedestrians and helps keep vehicle speed lower. Siteworx completed this project to a high standard and it is now used on a regular basis by many members of the public.
WORK COMPLETED
- Formed and poured raised pedestrian crossings
- Concreted & kerbed footpath
- Bollards installed
QUICK FACTS:
VALUE: $275,000
DURATION: August 2016 – November 2016 (3 months)
LOCATION: Gisborne, NZ
Civil Maintenance & Renewals
LJ Hooker Hockey Turf
WORK COMPLETED
- All drainage
- kerbing & concrete works
- light pole foundations
- asphalt preparation works
- Very high detail works, aggregate preparation plus or minus 10mm and asphalt plus or minus 3mm surface finishes
QUICK FACTS:
VALUE: $500,000
DURATION: November 2014 – February 2015 (3 Months)
LOCATION: Gisborne, NZ
Earthworks
Mitre 10 Gisborne
WORK COMPLETED
- All Storm-Water, Waste Water, Drinking Water & Bulk Earthworks
- Decontamination of site
- Chip seal & Asphalt, 5000m2
- Cement stabilize site, 12,000m2
- Concrete works, 3200m2
VALUE: 2,670,000
DURATION: February 2019 – February 2020 (1 Year)
LOCATION: Gisborne, NZ