Siteworx has just completed the Waikanae to Waipaoa Trail project. This consisted of 410m long, 3.5m wide path with timber bollards installed on one side. This is an additional path adding on to the Lions Junior Cycle track and Oneroa Cycle Track projects, that we have completed previously.
QUICK FACTS
- 410mx3.5m of concrete placing
- Bollard Barrier
- Kerbing
Mangapapa School Cycle Track
Siteworx recently installed a 350m concrete cycle track at Gisborne’s Mangapapa School, using a custom built 1.5m kerb machine to lay the concrete path – this proved to be a lot more efficient and more cost effective than the normal process of boxing.
This is part of a long-term school upgrade plan with recent carpark works just been completed the week before.
The track will be open to the public during weekends.
Oneroa Walkway – W2W
The Oneroa Walkway is part of Gisborne’s popular boardwalk is located along the dunes between Midway and Waikanae beaches. This walkway addition was to help make crossing the road safer for pedestrians and vehicles alike – the raised crossings created a designated crossing area for pedestrians and helps keep vehicle speed lower. Siteworx completed this project to a high standard and it is now used on a regular basis by many members of the public.
WORK COMPLETED
- Formed and poured raised pedestrian crossings
- Concreted & kerbed footpath
- Bollards installed
QUICK FACTS:
VALUE: $275,000
DURATION: August 2016 – November 2016 (3 months)
LOCATION: Gisborne, NZ